| Description |
Progress |
| Casting Yard – Overall Progress |
91.2% (as of 18 February 2009) |
| Pilling work |
100% |
| Batching Plant |
100% |
| Light Gantry Crane |
100% |
| General Building |
97% |
| Storage Yard |
100% |
| Infrastructural Works |
91.92% |
| M&E works |
73.2% |
| Mould Fabrication & Installation |
97% |
|
|
|
| Description |
Progress |
| Design Works |
12% |
|
|
|
| Description |
Progress |
| Jetty |
5% |
| Workers Camp |
5% |
|
|
|
|
|