Home : Core Business : Engineering & Construction : Penang 2nd Crossing Bridge : Progress Report

Casting Yard
Description Progress
Casting Yard – Overall Progress 91.2% (as of 18 February 2009)
Pilling work 100%
Batching Plant 100%
Light Gantry Crane 100%
General Building 97%
Storage Yard 100%
Infrastructural Works 91.92%
M&E works 73.2%
Mould Fabrication & Installation 97%

Bridge Superstructure
Description Progress
Design Works 12%


Enabling Works
Description Progress
Jetty 5%
Workers Camp 5%